School Renewal Investments Reporting

Font Size: A+ A- Reset

Limestone District School Board's School Renewal Investment Reports provide an overview of our efforts to replace and improve building systems across the district, including projects in planning, in progress, and completed:

Projects In Planning and In Progress

School and Project Name

Start Date

Estimated Complete Date

Status

Amherst Island Public School - Building Envelope

09/01/2023

12/31/2025

In Progress - Pre-Construction

Amherst Island Public School -Services

09/01/2024

08/31/2026

In Planning

Amherst Island Public School - Site

09/01/2025

09/01/2028

Long-Term Planning

Amherstview Public School - Interior Upgrades

09/01/2024

08/31/2025

In Planning

Amherstview Public School - Site Phase 1

09/10/2024

09/06/2026

In Progress - Pre-Tender

Amherstview Public School - Site 2

09/01/2025

08/31/2027

Long-Term Planning

Amherstview Public School - Structural

02/03/2023

09/04/2026

In Progress - Pre-Tender

Bayridge Public School - Interior Upgrades

09/01/2023

08/31/2027

Long-Term Planning

Bayridge Public School - Security/Access Upgrade

09/01/2023

08/31/2025

In Progress - Pre-Construction

Bayridge Public School - Site

09/01/2025

08/31/2026

Long-Term Planning

Bayridge Public School - Windows/Roof

09/02/2024

09/04/2026

In Progress - Pre-Tender

Bayridge Secondary School - Elevator Modernization

09/01/2024

08/31/2026

In Planning

Bayridge Secondary School - HVAC Upgrade

03/01/2023

08/31/2025

In Progress - Pre-Tender

Bayridge Secondary School - Mechanical Upgrades

09/01/2024

08/31/2025

Construction Greater Than 75%

Cataraqui Woods Elementary School - Electrical

01/01/2025

08/31/2025

In Progress - Pre-Construction

Cataraqui Woods Elementary School - HVAC Replacement

01/01/2025

08/31/2026

In Planning

Cataraqui Woods Elementary School - Lighting Replacement

09/01/2024

08/31/2025

In Progress - Pre-Construction

Cataraqui Woods Elementary School - Site Improvement

11/03/2023

08/31/2025

In Planning

Centennial Public School - Building Envelope

09/01/2022

08/28/2026

Long-Term Planning

Centennial Public School - HVAC Replacement

04/12/2022

08/29/2025

In Progress - Pre-Tender

Centennial Public School - Interior Improvement

09/01/2025

08/31/2027

Long-Term Planning

Centennial Public School - Site Development

09/22/2023

09/05/2025

In Progress - Pre-Tender

Central Public School - HVAC Phase II

10/06/2023

08/29/2025

In Progress - Pre-Tender

Centreville Public School - Structural Upgrade

09/01/2024

08/29/2025

In Progress - Pre-Tender

Clarendon Central Public School - Interior Upgrade

09/01/2024

08/31/2025

Construction Underway Less Than 25%

Collins Bay Public School - Site Improvements

09/01/2025

08/31/2027

Long-Term Planning

Elginburg and District Public School - HVAC/Roofing

09/08/2023

08/29/2025

In Progress - Pre-Tender

Elginburg and District Public School - Security Upgrade

09/01/2024

08/31/2025

In Planning

Elginburg and District Public School - Site Development

09/12/2023

09/08/2028

Long-Term Planning

Enterprise Public School - Roofing

09/01/2024

08/29/2025

In Progress - Pre-Tender

Enterprise Public School - Track and Fencing

09/12/2023

09/04/2026

In Planning

Ernestown Intermediate and Secondary School - Building Envelope

10/22/2023

09/05/2025

In Progress - Pre-Construction

Ernestown Intermediate and Secondary School - Fencing, Bus Loop and Entrance

05/02/2022

09/05/2025

In Progress - Pre-Construction

Ernestown Intermediate and Secondary School - Interior Improvements

09/01/2025

08/31/2027

Long-Term Planning

Ernestown Intermediate and Secondary School - Interiors Replacements

09/01/2024

08/31/2028

Long-Term Planning

Ernestown Intermediate and Secondary School - Roofing/Structural Upgrade

09/01/2024

08/31/2027

In Planning

Ernestown Intermediate and Secondary School - Site Improvement

10/25/2023

08/31/2026

Long-Term Planning

Ernestown Intermediate and Secondary School - Washrooms

09/07/2023

09/04/2026

In Planning

Fairfield Elementary School - Lighting and Ceiling

07/01/2024

08/31/2025

In Progress - Pre-Tender

Frontenac Secondary School - Building Envelope

09/19/2023

09/04/2026

In Progress - Pre-Construction

Frontenac Secondary School - Site Improvements Phase 1

05/02/2022

09/03/2027

In Progress - Pre-Tender

Frontenac Secondary School - WR Improvements

10/04/2024

09/04/2026

In Planning

Glenburnie Public School - Building Envelope Replacement

09/06/2024

08/29/2025

In Progress - Pre-Tender

Glenburnie Public School - Security/Access

09/01/2025

08/31/2026

Long-Term Planning

Glenburnie Public School - Site Improvement

04/01/2024

08/31/2025

In Progress - Pre-Tender

Granite Ridge Education Centre - Site Improvements

01/31/2024

09/05/2025

In Progress - Pre-Tender

Harrowsmith Public School - Site Improvements

09/12/2024

09/05/2025

In Progress - Pre-Tender

Harrowsmith Public School - Window Replacement

09/22/2023

09/05/2025

In Progress - Pre-Tender

J.G. Simcoe Public School - WR Upgrade

09/01/2024

08/31/2025

In Progress - Pre-Tender

Joyceville Public School - Site Improvements

09/01/2025

08/31/2027

Long-Term Planning

Joyceville Public School - Windows

09/01/2025

08/31/2027

Long-Term Planning

J.R. Henderson Public School - Lighting Replacement

09/01/2025

08/31/2027

Long-Term Planning

J.R. Henderson Public School - Site Improvements

09/12/2023

09/05/2025

In Progress - Pre-Tender

Lancaster Drive Public School - HVAC BR

07/01/2024

08/31/2026

Construction Greater Than 50%

Land O'Lakes Public School - Paving

09/01/2025

09/04/2027

Long-Term Planning

Land O'Lakes Public School - Structural

09/01/2025

09/03/2027

Long-Term Planning

Loyalist Collegiate Vocational Institute - Electrical Upgrade

09/01/2025

08/31/2027

Long-Term Planning

Loyalist Collegiate Vocational Institute - Gym Floor

09/22/2023

09/04/2026

Long-Term Planning

Loyalist Collegiate Vocational Institute - Interior Upgrades

09/01/2024

08/31/2025

Construction Underway

Loyalist Collegiate Vocational Institute - Masonry Phase #1

05/01/2023

09/05/2025

In Progress - Pre-Tender

Loyalist Collegiate Vocational Institute - Roofing

03/03/2025

08/28/2026

In Planning

Loyalist Collegiate Vocational Institute - WR Upgrade

06/18/2024

09/05/2025

In Progress - Pre-Tender

Strathcona Park Public School - Interior Replacements

09/01/2024

08/31/2028

Long-Term Planning

Loughborough Public School - HVAC/Lighting

07/01/2023

08/24/2025

In Progress - Pre-Tender

Loughborough Public School - Interior Upgrades

09/01/2024

08/31/2025

Construction Underway

Loughborough Public School - Site Improvements

09/12/2023

09/05/2025

In Progress - Pre-Tender

Limestone School of Community Education - Electrical/HVAC

09/01/2024

08/31/2025

In Progress - Pre-Tender

Limestone School of Community Education - Interiors Upgrades

09/01/2024

08/31/2025

Construction Underway

Limestone School of Community Education - Site Improvement - Phase 1

05/01/2024

08/31/2025

In Progress - Pre-Tender

La Salle Intermediate and Secondary School - Electrical Upgrade

07/01/2023

08/31/2026

In Progress - Pre-Tender

La Salle Intermediate and Secondary School - Interior Improvement

09/01/2023

05/30/2025

In Progress - Pre-Tender

La Salle Intermediate and Secondary School - Roofing Phase 2

09/01/2023

10/31/2025

In Progress - Pre-Tender

La Salle Intermediate and Secondary School - Roofing Phase 3/HVAC

09/01/2025

08/27/2027

Long-Term Planning

La Salle Intermediate and Secondary School - Site Improvements

09/01/2026

08/31/2027

Long-Term Planning

La Salle Intermediate and Secondary School - Site Improvements

09/01/2024

10/30/2026

In Planning

La Salle Intermediate and Secondary School - Tech Shop Upgrades

01/01/2025

08/31/2026

In Planning

École Maple Elementary School - Drainage Improvements

07/011/2025

08/31/2025

In Planning

École Maple Elementary School - Kinder Yard - Phase 2

09/24/2024

09/04/2026

In Progress - Pre-Tender

Marysville Public School - Envelope/HVAC

09/01/2026

08/31/2027

Long-Term Planning

Molly Brant Elementary School - Playground

08/16/2023

10/31/2028

Long-Term Planning

North Addington Education Centre - Interior Improvements

09/01/2025

08/31/2026

Long-Term Planning

North Addington Education Centre - Lighting Replacement

09/01/2024

08/31/2026

In Planning

North Addington Education Centre - Parking Lot / Bus Planning

09/22/2023

10/31/2028

Long-Term Planning

North Addington Education Centre - Roofing 2

09/01/2024

10/31/2025

In Progress - Pre-Tender

North Addington Education Centre - WR Upgrade

09/01/2024

09/04/2026

In Planning

Napanee District Secondary School - Masonry Review

09/22/2023

09/03/2027

In Planning

Napanee District Secondary School - Parking Lot/Bus Planning

11/08/2022

09/02/2028

Long-Term Planning

Napanee District Secondary School - Roofing

09/01/2024

09/30/2025

In Progress - Pre-Tender

Napanee District Secondary School - Welding Shop Renovation

03/01/2023

03/31/2025

Construction Greater Than 90%

Newburg Public School - Heating/Air Conditioning

05/27/2024

10/31/2028

Long-Term Planning

Newburg Public School - RAAC

09/01/2024

08/31/2027

Long-Term Planning

Odessa Public School - Traffic and Paving

05/02/2022

09/05/2025

In Progress - Pre-Construction

Odessa Public School - Windows and Doors

09/22/2023

09/03/2027

Long-Term Planning

Perth Road Public School - HVAC Replacement

09/01/2024

09/25/2026

In Planning

Perth Road Public School - Roofing

09/01/2021

08/29/2025

In Progress - Pre-Construction

Polson Park Public School - Interiors

09/01/2024

01/30/2026

In Progress - Pre-Tender

Polson Park Public School - Site Improvements

10/04/2023

08/31/2026

Long-Term Planning

Prince Charles Public School - Interiors

07/31/2024

09/05/2025

Construction Greater Than 75%

Prince Charles Public School - Structural Upgrade

09/01/2027

08/31/2028

Long-Term Planning

R.G. Sinclair Public School - Air Conditioning

07/08/2024

05/02/2025

In Progress - Pre-Construction

R.G. Sinclair Public School - Building Envelope Replacement

11/01/2023

08/31/2025

In Progress - Pre-Tender

R.G. Sinclair Public School - Drainage Review

05/02/2022

09/04/2026

In Progress - Pre-Tender

Rideau Public School - Elevator/Cladding Phase 2

09/13/2025

09/01/2028

Long-Term Planning

Rideau Public School - Paving

10/02/2020

09/05/2025

In Progress - Pre-Tender

Rideau Heights Public School - Building Envelope Review

10/02/2023

09/04/2026

Long-Term Planning

Rideau Heights Public School - Elevator/Renovations

12/04/2023

12/05/2025

In Progress - Pre-Tender

Rideau Heights Public School - Lighting Phase #1

09/05/2025

09/04/2026

Long-Term Planning

Rideau Heights Public School - Lighting Phase #2

09/05/2025

09/03/2027

Long-Term Planning

Rideau Heights Public School - Lighting Phase #3

09/04/2026

09/01/2028

Long-Term Planning

Rideau Heights - Site Accessibility Phase 2

10/02/2023

09/05/2025

In Progress - Pre-Tender

Rideau Heights - WR Upgrade

09/05/2025

09/03/2027

Long-Term Planning

Selby Public School - Building Envelope

09/02/2022

08/31/2025

In Planning

Selby Public School - HVAC Upgrade

09/01/2024

08/31/2026

Long-Term Planning

Selby Public School - Interiors

09/18/2024

09/05/2025

Long-Term Planning

Sydenham High School - Gym Partition

08/16/2023

09/04/2026

Long-Term Planning

Sydenham High School - HVAC

09/01/2025

08/31/2026

Long-Term Planning

Sydenham High School - HVAC/Electrical

09/01/2024

08/31/2026

Long-Term Planning

Sydenham High School - Roofing

09/01/2024

10/31/2025

In Progress - Pre-Tender

Sydenham High School - Window, Masonry (Phase 1)

07/01/2024

06/30/2025

Construction Greater Than 90%

Sydenham High School - Window, Roof (Phase 2)

09/01/2024

08/31/2027

Long-Term Planning

Southview Public School - Accessibility Improvements

09/01/2024

08/3/2025

In Planning

Southview Public School - HVAC Upgrade

04/07/2024

08/31/2025

In Progress- Pre-Tender

Sydenham Public School - Interiors and Accessibility

09/27/2023

09/01/2028

Long-Term Planning

The Prince Charles Public School - Floor Slab

11/28/2024

09/04/2026

In Progress - Pre-Tender

The Prince Charles Public School - Interior Improvements

09/01/2026

08/31/2027

Long-Term Planning

The Prince Charles Public School - Site Improvement

11/28/2024

09/05/2025

In Progress - Pre-Tender

Truedell Public School - Site/Traffic Calming

11/08/2022

09/05/2025

In Progress - Pre-Tender

Welborne Public School - HVAC Replacement

03/06/2024

08/29/2025

In Progress - Pre-Tender

Welborne Public School - Interior Upgrades

09/01/2023

08/31/2025

In Progress - Pre-Tender

Welborne Public School - Site Improvements

09/01/2024

09/01/2028

In Planning

Winston Churchill Public School - Building Envelope

09/18/2024

09/04/2026

Long-Term Planning

Winston Churchill Public School - Site Improvements

09/18/2024

08/31/2026

Long-Term Planning

Projects Completed

School and Project Name

Start Date

Completion Date

Status

Amherst Island Public School - Interior Upgrades

09/01/2023

10/16/2024

Completed

Amherstview Public School - Security System Upgrade

09/01/2023

08/31/2024

Completed

Amherstview Public School - WR Upgrade

0904/2023

10/31/2024

Substantially Completed

Bath Public School - Plumbing Update

09/01/2024

10/30/2024

Completed

Bayridge Secondary School - Lighting Replacement

09/01/2023

06/30/2024

Completed

Bayridge Secondary School - Mechanical Upgrades

09/01/2023

06/30/2024

Completed

Bayridge Secondary School - Roofing

09/01/2022

11/16/2023

Completed

Bayridge Secondary School - WR Upgrade

03/04/2022

10/21/2024

Completed

Cataraqui Woods Elementary School - Interior Upgrade

01/01/2024

08/23/2024

Completed

Cataraqui Woods Elementary School - Plumbing Replacement

09/01/2023

06/30/2024

Completed

Cataraqui Woods Elementary School - Roofing

01/01/2023

02/29/2024

Completed

Centennial Public School - WR Upgrades

09/01/2023

02/29/2024

Completed

Central Public School - HVAC Replacement

03/04/2021

12/31/2024

Substantially Complete

Central Public School - Interior Improvement

09/16/2022

08/31/2024

Completed

Centreville Public School - Life Safety System Upgrade

09/01/23

06/30/2024

Completed

Centreville Public School - Mechanical Upgrade

09/03/2021

02/29/2024

Completed

Centreville Public School - Plumbing Upgrades

09/01/2023

10/21/2024

Completed

Centreville Public School - Site Improvements

09/01/2023

10/22/2024

Completed

Clarendon Public School - HVAC Replacement

09/01/2023

12/01/2023

Completed

Clarendon Public School - Plumbing Replacement

07/01/2023

10/24/2023

Completed

Collins Bay Public School - HVAC Upgrade

04/01/2023

04/30/2024

Completed

Collins Bay Public School - Life Safety System Upgrade

01/01/2024

06/30/2024

Completed

Ernestown Intermediate and Secondary School - Electrical Service Upgrade

07/01/2022

12/20/2024

Completed

Ernestown Intermediate and Secondary School - Lighting Upgrade

09/01/2023

10/15/2024

Completed

Ernestown Intermediate and Secondary School - Mechanical Upgrade Phase 2

09/01/2022

10/23/2023

Completed

Ernestown Intermediate and Secondary School - Security System Upgrade

09/01/2023

06/30/2024

Complete

Fairfield Elementary School - HVAC Upgrade

09/01/2022

12/18/2023

Completed

Fairfield Elementary School - Yard Improvements

05/01/2024

11/30/2024

Substantially Complete

Frontenac Secondary School - Electrical and Lighting

04/30/2024

11/11/2024

Completed

Frontenac Secondary School - Gym Lighting

07/01/2024

01/09/2025

Substantially Completed

Gateway Community Education Centre - Flooring

09/01/2024

11/15/2024

Completed

Glenburnie Public School - Roofing

01/01/2024

09/30/2024

Completed

Granite Ridge Education Centre - Security System Upgrade

09/01/2023

04/22/2024

Completed

Granite Ridge Education Centre - Site Development

09/01/2022

10/23/2023

Completed

J.G. Simcoe Public School - Life Safety Upgrade

01/19/2023

09/30/2023

Completed

J.G. Simcoe Public School - Site Improvements (Phase 1)

09/01/2023

08/30/2024

Completed

Joyceville Public School - HVAC Upgrade

01/01/2023

12/01/2023

Completed

Joyceville Public School - Lighting Replacement

09/01/2023

10/16/2024

Completed

Joyceville Public School - Roofing Replacement

08/01/2023

11/27/2024

Completed

J.R. Henderson Public School - Interior Replacements

30/15/2024

08/31/2024

Completed

Land O'Lakes - Site Improvements

06/01/2024

12/13/2024

Completed

Land O'Lakes - Mechanical Upgrade

09/01/2022

01/01/2024

Completed

Loyalist Collegiate Vocational Institute - Interior Improvement

09/01/2023

11/22/2024

Completed

Loyalist Collegiate Vocational Institute - Lighting Replacement 1

01/01/2024

12/31/2024

Completed

Loyalist Collegiate Vocational Institute - Security System Upgrade

09/01/2023

04/22/2024

Completed

Loyalist Collegiate Vocational Institute - Site Improvement

09/01/2023

12/13/2024

Completed

Loyalist Collegiate Vocational Institute - WR Upgrade

09/01/2023

12/13/2024

Completed

Lord Strathcona Public School - Building Envelope Phase III and IV

09/01/2022

04/30/2024

Completed

Lord Strathcona Public School - HVAC, Lighting - Gym

10/01/2023

08/31/2024

Completed

Lord Strathcona Public School - Plumbing Upgrade

09/01/2024

12/31/2024

Substantially Complete

Lord Strathcona Public School - Site Development

09/01/2023

12/13/2024

Completed

Limestone School of Community Education - Controls Upgrade

07/01/2022

08/31/2024

Completed

Limestone School of Community Education - Lighting/Ceiling Replacement

07/01/2023

08/31/2024

Completed

Limestone School of Community Education - Security Access

06/30/2024

10/16/2024

Completed

La Salle Intermediate and Secondary School - Roofing 1

09/01/2023

11/22/2024

Completed

La Salle Intermediate and Secondary School - Security System Upgrade

09/01/2023

04/22/2024

Completed

La Salle Intermediate and Secondary School - Structural

09/01/2022

08/31/2024

Completed

Ecole Maple Elementary School - Site Improvements

09/01/2023

10/23/2024

Completed

Ecole Maple Elementary School - HVAC

01/01/2024

12/31/2024

Substantially Completed

Ecole Maple Elementary School - Security System Upgrade

09/01/2023

04/22/2024

Completed

Ecole Maple Elementary School - Site Improvements

09/01/2023

08/31/2024

Completed

Molly Brant Elementary School - Kinder Yard / Pedestrian Paths

09/01/2023

12/13/2024

Completed

Molly Brant Elementary School - Structural Review

09/01/2023

04/30/2024

Completed

North Addington Education Centre - Roofing

09/01/2023

09/16/2024

Completed

North Addington Education Centre - Site Improvement

05/01/2023

06/30/2024

Completed

Napanee District Secondary School - WR Upgrade

09/01/2022

12/15/2023

Completed

Newburg Public School - Lighting Replacement

09/01/2023

03/29/2024

Completed

Newburg Public School - Site Improvements

05/01/2023

02/12/2024

Completed

Newburg Public School - WR Upgrade

09/01/2022

10/23/2023

Completed

Odessa Public School - HVAC Upgrades

09/01/2022

12/19/2023

Completed

Odessa Public School - Site Improvement

09/01/2023

07/05/2024

Completed

Polson Park Public School - HVAC Replacement

09/01/2022

0/29/2024

Completed

R.G. Sinclair Public School - Roofing

09/01/2021

01/09/2024

Completed

R.G. Sinclair Public School - Roofing and Windows

11/01/2023

01/31/2025

Completed

R.G. Sinclair Public School - WR Upgrades

06/01/2023

04/30/2024

Completed

Rideau Public School - Roofing and Cladding

07/01/2023

12/31/2023

Completed

Rideau Heights Public School - Interior Improvement

01/01/2023

06/30/2024

Completed

Rideau Heights Public School - Roofing

09/01/2022

10/23/2023

Completed

Rideau Heights Public School - Security System Upgrade

09/01/2023

11/06/2023

Completed

Rideau Heights Public School - Site Accessibility

09/01/2023

06/30/2024

Completed

Selby Public School - HVAC Upgrade

09/01/2023

08/31/2024

Completed

Selby Public School - Paving

09/01/2023

02/01/2024

Completed

Sydenham High School - Elevator Modernization

09/01/2023

08/31/2024

Completed

Sydenham High School - Front Yard Upgrades

09/01/2023

06/30/2024

Completed

Sydenham High School - Security System Upgrade

09/01/2022

11/01/2023

Completed

Southview Public School - Site Improvements

05/31/2023

08/31/2024

Completed

Sydenham Public School - Controls Upgrade

07/01/2023

08/31/2024

Completed

Sydenham Public School - Roofing

09/01/2022

09/29/2023

Completed

Tamworth Elementary School - Accessibility Study

09/01/2023

05/08/2024

Completed

Tamworth Elementary School - Paving

05/01/2023

01/12/2024

Completed

The Prince Charles Public School - Plumbing Replacement

09/01/2023

10/16/2024

Completed

The Prince Charles Public School - Site Improvements

09/01/2021

01/03/2024

Completed

Truedell Public School - Roofing, Doors, and Windows

09/01/2021

01/03/2024

Completed

Welborne Avenue Public School - Roofing

09/01/2022

09/29/2023

Completed

W.J. Holsgrove Public School - Mechanical Replacements

09/01/2023

06/30/2024

Completed

W.J. Holsgrove Public School - Site Repairs

09/01/2023

06/30/2024

Completed



Kindergarten Registration